Call Us Toll Free 1-800-606-3564
 
 

Buying/Selling In Guanacaste
Home Page
View All Property Listings
Virtual Tours
Sell Your Property
Contact Us
 
Guanacaste Articles
Number of tourist coming to Guancaste continues upswing.
Tree planting in Playas del Coco
Playas del Coco Marina Project Marches On
 
Area Activities and Information
Guanacaste Beaches: Something for Everyone
5 National Parks within a Few Hours Drive
Day Tripping in and around the Papagayo Gulf.
Hola Divers
Scuba Diving around Guanacaste
Fishing Coco and Ocotal
Blue Marlin Service (Ocotal Fishing)
Arroyo Adventures and Jetskis (Coco)
Resort Divers (Playas del Coco)
Surfing around Playas del Coco
Guidlines for Visiting Guanacaste Costa Rica
Foreign Investment In Costa Rica
Renting a Car While Yur Here
all activites




When considering this opportunity we feel it is important that our investors have a good understanding of our successes. Agua de Lechuga is a condominium project consisting of 39 units located 4 blocks from Coco beach.
Planning for this project began in February 2007, the design process was completed in 2 months time.

Several factors were attributed to the success of Agua de Lechuga, location and price point were the primary reasons. We understand our market and
this is why choosing a proper price point and managing construction costs is so important to a projects success. Less than 6 months after original buyers reserved their units, prices were up 30%. Buyers were reselling their unit before the second payment became due.

Permits for the project took approximately 9 months with pre-sales begining right after the design process was completed. The project had been 85% sold by the time all permits were acquired. We officially broke ground in April 2008. We expect the project to be completed in 10-12 months.

The timelines associated with permit acquisition vary drastically from project to project. Although we know we can expedite the permitting process you will notice a 2.5 year timeline in the investor agreement. Project success is priority #1, thus the timeline is in place to protect it. Further details and construction photos can be found at www.aguadelechuga.com The permiting process has already begun for Phase2. Some of our other projects currently under development include, Rio del Monte, Bella Flora and Victoria.

 

 

 