When considering this opportunity we feel
it is important that our investors have a good
understanding of our successes.
Agua de Lechuga is a condominium project consisting
of 39 units located 4 blocks from Coco beach.
Planning for this project began in February 2007,
the design process was completed in 2 months time.
Several factors were attributed to the success of Agua
de Lechuga, location and price point were the
primary reasons. We understand our market and
this is why choosing a proper price point and
managing construction costs is so important to a
projects success. Less than 6 months after original
buyers reserved their units, prices were up 30%.
Buyers were reselling their unit before the second
payment became due.
Permits for the project took approximately 9 months with pre-sales begining right after the design process was completed. The project had been 85% sold by the time all permits were acquired. We officially broke ground in April 2008. We expect the project to be completed in 10-12 months.
The timelines associated with permit acquisition vary drastically from project to project. Although we know we can expedite the permitting process you will notice a 2.5 year timeline in the investor agreement. Project success is priority #1, thus the timeline is in place to protect it. Further details and construction photos can be found at www.aguadelechuga.com The permiting process has already begun for Phase2. Some of our other projects currently under development include, Rio del Monte, Bella Flora and Victoria.
|